Motueka Stormwater Improvements - Poole, Wilkie & Jocelyn Streets

This project covered works to improve the stormwater services on Poole and Wilkie Streets in Motueka.  The project was completed in July 2018.

About the Project

To reduce the risk of flooding, we installed additional stormwater pipework on Poole, Wilkie and Jocelyn Streets. The extra capacity will reduce the stormwater run-off from the road into private properties in the area.

Poole Wilkie streets stormwater upgrade map

Back to Top

Timeline & Progress

Downer NZ began work in early February 2018 and completed work in early July 2018.  The project was delayed as the Downer team were reassigned to urgent reparation work following Cyclone Gita. 

The tendered cost for the work was $597,640.43.   The total cost of the work came in under budget at $575,676.00.

Back to Top

More Information

For more information email projects@tasman.govt.nz or contact the Project Manager, Graham Rimmer, on 03 543 8631.